
Highland Street Utility Project

Construction is Underway!
Check out recent drone footage below.

your
brand

Recent Activities
SUMMARY OF MAJOR CONSTRUCTION ACTIVITIES-MARCH 2023
Sheathing and air-vapor barrier is ongoing in Building E. The roofing work has been completed. Masonry veneer is complete on north elevations of A, D, and E buildings; work is ongoing at the west elevation of Building E1. Kalwall installation is ongoing and the skylight installation has started. The metal panels installation continues on Buildings B & C. The drywall contractor continues framing walls in area A and has begun sheetrock in Building C. Mechanical, electrical, plumbing and fire protection contractors are continuing their rough-in work in all areas. Curtainwall and Windows continue to be installed in C, B and E buildings. Stair A2 was installed; Stair A1 install is ongoing. Temporary winter enclosures and temporary heat provisions were maintained.
ONE MONTH LOOK AHEAD
-
Continue Masonry Veneer
-
Continue curtainwall, window and metal panel installation
-
Continue Kalwall and skylight installation
-
Continue MEP rough-in
-
Continue Sheathing and AVB
-
Continue sheetrock and taping