top of page



Highland Street Utility Project

 

For information on the Highland Street Utility Project please click Here

Click Here to view exciting drone footage coming from INSIDE the Doherty Memorial High School Jobsite! A huge thank you to Josh Wingell who used state-of-the-art drone technology to fly inside the school and capture the progress being made.

Rendering- LPA Doherty.jpg

Construction is Underway!
Check out recent drone footage below.

your

brand

READ MORE
Recent Activities

SUMMARY OF MAJOR CONSTRUCTION ACTIVITIES - February 2024

Demo and abatement of the existing building began in June. The sitework at the west side of the building began with the installation of the Underground Recharge System #3. The main entrance paver installation continued. At the north side of the building, the sidewalk installation began. The work at the veneer stone wall along Highland continued. Plantings along the east and south sides of the building continued. The curb and sidewalk at the south side of the building was installed. The curtain wall subcontractor is wrapping up install of interior storefronts and aluminum frames. Ceiling tile installation wrapped up throughout the building. The blade ceiling installation in the Lobby was completed. Terrazzo floor tile install in the lobby and servery were completed. Epoxy flooring was completed at the CCL classrooms and corridor.

 

The hardboard floor installation at the Blackbox Theater continued. The acoustic panels in the music rooms and Blackbox were installed. Gym wood floor installation continued. The rubber athletic flooring installation was completed. Flooring installation continued in the ground floors and the connector corridors. In the Auditorium, the laminate panel installation finished, and the stage maple floor installation began. The carpet install at the Auditorium aisles began.

 

The acoustic drywall ceiling installation at the Lobby and Cafeteria was completed. The Lobby interior ceramic panel installation continued. Stainless cladding at the Lobby and Cafeteria continued. The Lobby laminate panel installation began. Signage installation continued. Final cleaning and punch list continues in the academic wings. Furniture installation began on 6/6.

bottom of page