top of page



Highland Street Utility Project

 

For information on the Highland Street Utility Project please click Here

Click Here to view exciting drone footage coming from INSIDE the Doherty Memorial High School Jobsite! A huge thank you to Josh Wingell who used state-of-the-art drone technology to fly inside the school and capture the progress being made.

Rendering- LPA Doherty.jpg

Construction is Underway!
Check out recent drone footage below.

your

brand

READ MORE
Recent Activities

SUMMARY OF MAJOR CONSTRUCTION ACTIVITIES - December 2023

The East Road plantings and timber guard rail were installed. The placement of site walls in the B/C and A/B courtyards is on-going. Installation of the remaining west side site walls is underway. The curtain wall installer continues to install snap trim and sunshades at all elevations at Buildings E and D. Metal panel installation continues at the roof. Drywall continued in Building E main floor, as well as Building E ground floor and Building D science rooms. The drywall in stairs D1 and D2 is on-going. Casework was completed in Buildings A and B; casework is on-going in Building D. Corridor tile install continued in Buildings A and B, and began in Building D. The locker room tile began in Building D. Locker install in Building C was completed, and began in Building B. The Building D locker room locker install began. Flooring installation continued in the Building B classrooms. MEP OH rough-in and in-wall rough-in continues in Building E. Elevator 2 install is majority complete. Auditorium high work continues from the working platform, the ceiling panel install began. The stage rigging installation continues. The mechanical room fit out is on-going.

 

 

ONE MONTH LOOK AHEAD

  • Curtain Wall install will continue at Building E and D

  • Metal Panel installation will be complete

  • Drywall in Building E will continue

  • Paint will continue in Building E

  • Ceiling grid to continue in Building D and begin in Building E

  • Casework install to continue in Building D

  • Corridor wall tile will continue in Building D. The locker room tile will continue. Wall tile will begin in stair C2.

  • West side site walls will be complete

  • B/C courtyard site walls will be complete

  • A/B courtyard site walls will be complete

bottom of page